This project provided a unique septic system for a commercial customer in Sundance, WY. This project is unique because it required a pump, floats, and alarm system to move wastewater from the septic tank to the leachfield.
We installed piping from the building into two septic
tanks. The first septic tank functions to house the wastewater and the
second tank to house a pump. From the tank to the leachfield we
installed 150 feet of pressure line to a distribution box and then to 150 feet
of chambered leachfield.